Worcester Zoning Ord. art. IV

Citation
Worcester Zoning Ord. art. IV 1.
Parent Document
Worcester Zoning Ord. art. IV
Jurisdiction
Worcester (municipal)

Other Sections in This Document (1154)

Full Text

714 chars
1. At least sixty (60), but no greater than ninety (90), days prior to construction, the
        applicant shall obtain the requisite permit from the Department of Public Works and
        Parks approving the route and method of transporting the equipment and parts for the
        construction, operation or maintenance of the WECF. In addition to the permit
        requirements promulgated by the commissioner of DPWP, the applicant shall submit,
        with its request for a permit, a report identifying all state and city streets within the city
        of Worcester to be used as its transport route. A copy of the report shall also be
        submitted to the Division of Planning and Regulatory Services.